Building work price list: Gas Pipe Relocation and Connection
Enter quantities and the price recalculates instantly. You can adjust the rates in your price list.
All prices shown exclude VAT. Labour price covers labour only. Price incl. materials adds sundry materials (adhesive, primer, sealants, fixings). Tiles, flooring, paint and sanitaryware are chosen and bought by the client and are not included.
| Item | Unit | Price / unit | Quantity | Total |
|---|---|---|---|---|
Gas installations cost | ||||
| Relocate and reconnect gas pipework | pcs | €129.00 / pcs | pcs | enter quantity- |
| Forming and welding internal gas piping | lm | €18.00 / lm | lm | enter quantity- |
| Laying external gas main in ground | lm | €15.00 / lm | lm | enter quantity- |
| Chasing gas pipe - brickwork | lm | €15.00 / lm | lm | enter quantity- |
| Chasing gas pipe - concrete | lm | €35.00 / lm | lm | enter quantity- |
| Install gas ball valve | pcs | €15.00 / pcs | pcs | enter quantity- |
| Connect gas cooker | pcs | €55.00 / pcs | pcs | enter quantity- |
| Connect gas boiler (install & hook up) | pcs | pcs | - | |
| Boiler commissioning and set-up | pcs | pcs | - | |
| Blank off gas pipework | pcs | pcs | - | |
| Install DHW cylinder | pcs | pcs | - | |
| Gas pipeline pressure test | pcs | €90.00 / pcs | pcs | enter quantity- |
| Gas appliance inspection (safety check) | pcs | pcs | - | |
| Install gas leak detector | pcs | €35.00 / pcs | pcs | enter quantity- |
| Relocate gas meter | pcs | €150.00 / pcs | pcs | enter quantity- |
When gas pipework needs to be moved or extended
The gas engineer alters the existing gas installation in a flat or house so that it runs to a new position. This usually comes up during a kitchen refit, a change of layout, or when an old heating system is replaced with a new boiler. The work is one part of gas fitting work in the home.
A typical case: in the new kitchen the hob will sit on a different wall from the old cooker. The old gas point then ends up behind the units or in the middle of a cupboard. It has to be extended or moved.
The same applies when old gas water heaters are replaced with a boiler feeding radiators or underfloor heating. Gas is brought to one new position. The old points are disconnected and capped.
It is important to tell two things apart:
- altering the internal installation: the pipework after the meter already exists and only its route changes or a new outlet is added. This page covers that work,
- a new gas service connection: the property is not yet connected to the gas network, or the connection point is changing. That is a separate and more involved matter handled by the gas network operator.
If gas will no longer be used in the property at all, the supply is ended. The meter is then normally removed and the supply capped before the meter or at the emergency control valve. More on this is in capping off the gas supply at the meter.
What to decide before calling a gas engineer
The engineer needs to know exactly where the pipe will run and what will be connected to it. The clearer this is, the more accurate the quote and the less rework later.
- Exact appliance position: for a kitchen, have the final unit layout with dimensions, the position of the hob or cooker and the cabinet below it. The outlet is placed so the isolation valve is accessible and the hose is short.
- Type of appliance: a freestanding cooker, a built-in hob and a boiler each have different connection and positioning requirements. For a boiler, the flue and air supply also matter. The engineer installing the boiler deals with this.
- Surface-run or concealed pipe: a surface-run pipe is simpler and cheaper. A pipe buried in a chase or behind tiling looks better but has stricter rules. Decide in advance, because tiling and plasterboard are planned around it. Chases are cut either in brickwork or in concrete, and each affects time and cost differently. In homes built before 2000, have suspect materials tested before you drill or demolish; asbestos insulating board, lagging and sprayed coatings must be removed by an HSE-licensed contractor.
- Future appliances: if a gas boiler might replace electric heating in a few years, tell the engineer now. A capped branch fitted during the refurbishment saves breaking out walls later.
- Replacing old pipework: during a larger refurbishment, consider replacing old pipework at the same time while the walls are open.
- Who handles the paperwork: agree whether the engineer arranges the documentation, certificates and any notifications, or leaves this to you.
Who may move gas pipework and what paperwork is needed
Gas work is strictly regulated. In the UK only an engineer on the Gas Safe Register, qualified for the type of work involved, may work on gas pipework and appliances. A handy neighbour or a general plumber without Gas Safe registration must not do it, even for a few centimetres of pipe. That is why this page contains no DIY instructions.
Before work starts, check:
- Gas Safe registration: ask to see the engineer's Gas Safe ID card before agreeing a date and check the categories of work on the back,
- documentation: whether a simple sketch is enough for your scope, or whether a proper design is needed,
- the network operator and supplier: if the work involves the meter or the emergency control valve, or the supply arrangement changes, contact them first, as the meter and the pipework up to it are not yours to alter,
- building control: some gas work, such as installing a new boiler, must be notified. A Gas Safe registered engineer normally does this through the Gas Safe Register scheme and you receive a compliance certificate. Do not assume nothing is needed - confirm with the engineer,
- consent in a block of flats: if the work touches the riser or communal areas, agree it with the managing agent or freeholder.
Gas installations in buildings must comply with the Gas Safety (Installation and Use) Regulations 1998 (Northern Ireland has its own 2004 Regulations), the applicable standards and the manufacturers' instructions. Domestic gas pipework should be installed and tested to BS 6891:2015+A1:2019 by a Gas Safe registered engineer. Compliance is the responsibility of the engineer and, where there is one, the designer. You should receive written proof that the work was done and tested correctly.
Step-by-step: how gas pipework is relocated
- Survey. The engineer inspects the existing pipework, its material, the position of valves and the location of the new appliance. They assess whether a short alteration will do or a new route is needed.
- Design and documentation. Depending on the scope, a design or at least a technical sketch is prepared showing the route, pipe size, material and valve positions. For larger changes or a change to the supply, the network operator may require it.
- Isolation and purging. The gas supply is turned off before work starts. In a block of flats, this is coordinated with the managing agent if a shared valve on the riser must be closed. The engineer safely releases gas from the affected section and confirms none remains.
- Installation. The old outlet is cut back or capped and the new pipe is laid. An isolation valve is fitted before the appliance and the appliance is connected, for a cooker usually with an approved flexible cooker hose.
- Tightness test. The altered installation is pressurised and watched for the required time to make sure the pressure does not drop. Joints are also checked with a detector or leak detection fluid. The test pressure and duration are recorded.
- Certification, purging and commissioning. The engineer completes the safety checks and issues the relevant certificate or record of work. The installation is then filled with gas and purged so no air remains. Finally, the appliance is lit and set up.
- Making good. A pipe in a chase or behind plasterboard is covered only after a successful tightness test.
A simple cooker point relocation usually takes the engineer a few hours. A larger alteration in a house may take several days, including preparing documentation and certification.
Cost of relocating gas pipework: what it depends on
The guide labour price in the price list is €129.00 per piece. A piece normally means one relocation or connection of one outlet for one appliance. Certification and design are usually separate items, with guide prices in the price list higher up the page. When comparing quotes, ask what is included: materials, valve, hose, tightness test, certification and documentation. The final amount depends mainly on:
- distance and route: a short move along the same wall is simple. Passing through several walls or rooms needs more material and time and can multiply the price,
- condition of the old pipework: old galvanised steel pipe with corroded threads often cannot be safely connected to. Replacing a section then becomes necessary, which was not originally planned,
- surface-run or concealed: surface-run pipe is cheapest. Concealing it in the wall adds chasing, making good and more demanding joints,
- number of appliances and outlets: each extra outlet, valve or capped old point is charged separately,
- block of flats: shutting off a whole riser requires coordination with the managing agent and neighbours. Limited working time increases the effort,
- extent of documentation: whether certification alone is enough, or a design and the network operator's input are needed. Design and administration cost extra on top of the installation itself.
How to prepare so the engineer is not kept waiting
Good preparation on your side saves a lot of time:
- clear access to the pipework: empty cupboards, pull out the old cooker and clear the way from the meter or riser to the new appliance position,
- first-fix work finished: demolition, bricklaying and chasing for other services should be done so the new pipe is not damaged,
- final kitchen or boiler room layout with dimensions, so the outlet does not have to be moved later,
- appliance on site: if the cooker or boiler is to be connected and set up straight away, it should be delivered and unpacked, with its instructions,
- agreed shut-off in a block of flats: the managing agent and neighbours must know the riser shut-off date in advance,
- certification arranged: when the checks and paperwork are completed straight after installation, the gas is back on sooner.
The job takes longer if the engineer finds on site that the appliance is in a different place from the one agreed. Pipework covered by furniture or tiling, or a riser shut-off nobody was told about, also cause delays.
Typical mistakes in gas alterations and how they show up later
No certification. Without a record of testing and certification, the altered installation has not been shown to be safe to use, even if it seems to work. The problem surfaces at an inspection, when selling the property or after an incident, when the insurer may refuse to pay. For owner-occupiers there is no legal inspection cycle, but HSE strongly advises a safety check and service by a Gas Safe engineer every 12 months; for landlords the annual check is a legal requirement.
Wrong material or joints. Only materials and fittings intended for gas may be used, for example steel, copper or certified systems. Threads must be sealed with a product approved for gas. Unsuitable sealant can loosen over time and the joint starts to leak.
Covered valve or joint. A valve before the appliance that is plastered in or hidden behind a cabinet without a door cannot be closed quickly in a gas leak. Any repair then means breaking out.
Cooker hose too long or kinked. The hose must be approved and as short as possible, usually no more than 1.5 m. It must not be stretched or touch hot parts of the oven. A kinked or overheated hose deteriorates faster and may start to leak.
Old outlet only turned off. An unused outlet left with only a closed valve can be opened by mistake. The correct solution is to cap it properly.
Planning only for today. Without thinking about future appliances, walls get opened up again a few years later, often through finished tiling.
If you ever smell gas, do not switch lights or appliances on or off, turn off the gas at the emergency control valve, open windows and go outside. Call the free 24-hour National Gas Emergency Service on 0800 111 999 (0800 002 001 in Northern Ireland). For LPG, call the number shown on the tank or meter. Call the network, not your energy supplier.
How to check relocated gas pipework at handover
Before the engineer leaves, go through these points together:
- the pipe is firmly fixed, with no bends or visible damage,
- there is an accessible isolation valve before the appliance and you know how to close it,
- you know where the emergency control valve for the flat or house is,
- old unused outlets are properly capped,
- the cooker hose is approved, short, not stretched or kinked,
- the appliance burns with an even blue flame and the flame safety device works,
- there is no smell of gas near the joints,
- you have the tightness test record and the certificate, dated and signed by the Gas Safe registered engineer,
- you have documentation or a sketch of the new pipe route, especially if it is concealed in the wall,
- you know whether anything must be notified to the network operator, managing agent or building control, and who will do it.
Frequently asked questions
Roughly €129.00 per piece, meaning one relocation or connection of an outlet. The final amount depends on route length, the condition of the old pipework, whether the pipe runs on the surface or in the wall, and whether certification and documentation are included.
No. Only a Gas Safe registered engineer may work on a gas installation. DIY gas work is illegal and puts you and your neighbours at risk. The supply can be cut off as unsafe, and if damage occurs you may have problems with your insurer.
Yes. After any alteration to the pipework, however small, a tightness test and safety checks are carried out and recorded. This is proof that the alteration is gas-tight and safe.
Under certain conditions yes, but the rules are stricter than for surface-run pipe. Usually there must be no mechanical joints in the concealed section and valves must remain accessible. The engineer will propose a compliant solution.
It depends on the scope. If the supply arrangement changes or the meter is involved, contact the network operator or supplier. Some work, such as fitting a new boiler, is notifiable to building control, which the Gas Safe registered engineer normally handles. In a block of flats, also contact the managing agent.
For a simple outlet relocation, usually only part of a day. For a larger alteration or in a block of flats where the whole riser is shut off, the shut-off is planned in advance. It can last longer until testing and certification are complete.
An unused outlet is cut back or properly capped, and its tightness is checked during the tightness test. Leaving it with only a closed valve is not an acceptable solution.
Related work
How wall chases for gas pipes are cut in brick and concrete, which rules apply to the route, common mistakes and how to check the finished work.
How chases for gas pipes are cut into concrete, what to prepare, how to deal with reinforcement and how to check the chase before it is filled.
When a gas pipe is blanked off, what to arrange with the gas network operator, how a registered gas engineer does the job and what paperwork to keep.
How a gas boiler is fitted and connected, who may do the gas work, which documents you should receive and what to check at handover.
How a hot water cylinder is fitted and connected to the boiler and mains, what makes the job harder and what to check at handover.
How a gas safety inspection works, when you need one, who may carry it out and what the inspection report or certificate should contain.
Price the whole project, not just one job
Choose items from all trades and NUMIQ turns them into a quote for your own project or your customer's project.