Installation and Bedding of a Shower Channel

A shower channel is a narrow linear drain set into the floor of a level-access shower. Fitting it, connecting it to the waste and bedding it in screed costs roughly €140.00 per piece. Floor height and waste position affect the price most.

Updated 09/2026·12 min read·27 price list items
Standard labour price
€140.00/ pcs
Indicative range
€112.00 - €182.00
Price for this specific task only - excluding materials and preparatory work. Not the price of the whole job.
Price my renovation
Updated prices
On this page

Building work price list: Installation and Bedding of a Shower Channel

Enter quantities and the price recalculates instantly. You can adjust the rates in your price list.

Plumbing27 items

All prices shown exclude VAT. Labour price covers labour only. Price incl. materials adds sundry materials (adhesive, primer, sealants, fixings). Tiles, flooring, paint and sanitaryware are chosen and bought by the client and are not included.

ItemUnitPrice / unitQuantityTotal

Plumbing works cost

Install shower channel + screed inpcs€140.00 / pcspcsenter quantity-
Installation of wall-hung WC duct framepcspcs-
Install and fit access panelspcs€45.00 / pcspcsenter quantity-
Installation of concealed WC framepcs€120.00 / pcspcsenter quantity-
Install and brick-up bathpcs€90.00 / pcspcsenter quantity-
Install ceramic basinpcs€50.00 / pcspcsenter quantity-
Shower tray installationpcs€130.00 / pcspcsenter quantity-
Install shower enclosure glass (screen)pcspcs-
Installation of shower enclosurepc€150.00 / pcpcenter quantity-
Install deck-mounted tappcs€35.00 / pcspcsenter quantity-
Install wall-mounted bath/shower mixerpcs€65.00 / pcspcsenter quantity-
Install concealed shower valve body (iBox)pcspcs-
Install concealed mixer tappcspcs-
Cold and hot water outlet pointpcs€35.00 / pcspcsenter quantity-
Internal waste and drainage outlet pointpcs€25.00 / pcspcsenter quantity-
Install washing machine/dishwasher valve and trappcspcs-
Hang and connect electric water heater up to 120 lpcs€104.35 / pcspcsenter quantity-
Install whole-house water filterpcs€55.00 / pcspcsenter quantity-
Installation of domestic sewage treatment plant / septic tank on gravel bedpc€600.00 / pcpcenter quantity-
Hot water circulation pipeworklmlm-
Pressure test internal water supply pipeworkhrhr-
Chase cutting for plumbing (concrete)lm€29.00 / lmlmenter quantity-
Make good walls after plumbinglm€8.50 / lmlmenter quantity-
Install and chase in concealed valve bodypcs€95.00 / pcspcsenter quantity-
Install stopcocks / isolation valvespcs€13.00 / pcspcsenter quantity-
Install valve for dryer/washer + wastepcs€55.00 / pcspcsenter quantity-
Connect pipework to cast iron waste stackpcspcs-
Total labour
- enter quantity
Create quote from price list →

What installing a shower channel involves and when it is needed

In a shower without a tray, water drains through a channel recessed into the floor. The plumber sets the channel body at the correct height, connects it to the drainage and beds it firmly in the screed so the floor falls towards the outlet. This work is part of a new build or a larger bathroom refurbishment, when the old floor is broken out and a level-access or wet room style shower is wanted. A shower with no step is also easier to use in later life.

A channel has several advantages over a conventional shower tray. The floor is continuous, the tiles run from the bathroom into the shower, and cleaning is easier. However, all the work ends up hidden under screed and tiles. A mistake in the fall, height or sealing can only be put right by breaking the floor out again. That is why preparation and checks before the screed goes down matter more here than with most bathroom work.

Position, channel type and floor fall: what to decide in advance

Most decisions need to be made before the plumber arrives with the channel. Once the screed is laid, the position and height of the channel cannot be changed.

Where the channel will go

The channel is most often placed along a wall. The floor then falls in one direction only, the tiles are easier to cut and water drains evenly. A channel in the middle or at the entrance to the shower is used when the layout requires it. The fall is then more complicated and the tiles have to be cut in several directions.

Outlet type and build-up height

Channels are made of plastic or stainless steel. A plastic body is light and entirely adequate for a normal domestic shower. Stainless steel channels are more durable and are chosen where the shower is used heavily or a more robust solution is needed. More important than the material are the outlet type and the build-up height:

  • Horizontal outlet leaves from the side and connects to a waste pipe run within the floor. It is the most common type, but it needs enough depth in the floor build-up.
  • Vertical outlet goes straight down, for example into the ceiling void below the bathroom or into a prepared pipe. It is used when there is no room in the floor for a horizontal run.
  • Low-profile channels with a reduced build-up height help in refurbishments where the floor cannot be raised much.

A good-quality floor drain has a trap with a water seal that keeps out drain smells and is manufactured to the applicable standards. It is worth checking this in the channel's technical data sheet.

Which tiles and how thick

The channel height is set to suit the finished tiles. Its top edge must sit flush with them, in the same plane. The plumber therefore needs to know the thickness of the tiles, the adhesive bed and the tanking before fitting the channel. Some channels have a tray-style grate into which a strip of tile is inserted. This also needs to be decided in advance.

Underfloor heating

If the bathroom will have underfloor heating, its pipes must be coordinated with the position of the channel and the waste pipe, and with the screed depth. The heating engineer and the plumber should agree the layout before anything is fitted, so that the two installations do not clash in the same place. Wet underfloor heating should be installed and pressure-tested to BS EN 1264-4 before the screed is laid.

Soil stack, consents and building control

In a block of flats, check before starting where the shared soil stack runs and whether any work on it needs consent from the freeholder or managing agent. The lease may also require permission for alterations to the floor. If the structure would be altered or the ceiling broken out more extensively, seek advice from local authority building control. Whether any approval is needed depends on the scope of the work, so always confirm this directly.

How to bed a shower channel step by step

The method varies with each product, so the plumber always works from the manufacturer's installation instructions. The principle, however, is similar:

  1. Checking the waste: the waste pipe is checked to make sure it is clear and clean and that its position allows the connection. The pipe under the screed must fall towards the soil stack, typically 1 to 3 %. With less fall, water drains slowly and the waste blocks up.
  2. Preparing the base: the base is cleaned and levelled. It must be sound, without cracks or voids.
  3. Perimeter strips: edge insulation strips are laid along the walls so the screed does not bear against them.
  4. Setting the channel: the channel is placed on adjustable feet or brackets. The height is set so that the top edge will later be flush with the tiles. A spirit level is used to check it lengthways and crossways.
  5. Connecting to the drainage: the channel outlet is connected to the drainage, usually with plastic push-fit waste pipe. The joint must be watertight but slightly flexible.
  6. Water test of the joint: water is poured into the channel to check that it drains smoothly and that the joint does not drip.
  7. Bedding in: the channel is taped over to keep screed out and is then bedded in gradually. The mix is spread evenly and packed firmly underneath the channel, so it does not shift and no voids remain below it.
  8. Fall and curing: the screed is ruled off to a fall towards the channel and left to cure.

The checks in steps 1, 4 and 6 are the most important, as they cannot be repeated once the screed is laid. Once the screed has cured, tanking and a watertightness test of the whole shower area follow.

Tanking and watertightness test

Bedding the channel in screed does not make the shower watertight. Cement screed lets water through, so a flexible tanking membrane or slurry is applied to the finished, cured base, usually in two coats. Sealing tapes are embedded in the first coat at internal corners, at the wall-to-floor junction and around the channel. Many channels come with a factory-fitted sealing collar that is laid straight into the tanking.

The highest-risk points are the joint between channel and tanking and the corner where the channel meets the wall. A leak there often only shows after months, for example as a damp patch on the wall of the next room or on the ceiling of the flat below.

Tanking must not be applied too early. For cement screed, a rule of thumb is around one week per centimetre of thickness, and longer for thicker layers. The screed can usually be walked on after a few days. The exact times are given by the screed manufacturer, and if in doubt the moisture content can be measured before tanking. During curing, the screed should be protected from draughts and direct sunlight.

Once the tanking has dried according to the manufacturer's instructions, the channel outlet is plugged and the shower area is flooded with water a few centimetres deep. The water is usually left to stand for around 24 hours. Then it is checked whether the level has dropped and whether damp has appeared anywhere, including on the wall of the next room or in the property below. Tiling only starts once it is clear that no water is escaping.

What affects the price of installing a shower channel

The guide price for the labour is €140.00 per piece. It applies to a standard case: a waste ready in the right place, enough floor depth and a sound base. The final figure depends on these factors:

  • Floor depth: if there is too little, a low-profile channel is needed, a channel has to be cut into the base or the whole floor raised. Chasing channels in concrete and raising the floor are extra items, priced separately, and increase the cost noticeably.
  • Waste position: if the waste is not where the channel will go, the pipe must be moved or extended. A short extension adds less; rerouting across the whole bathroom with chasing can even double the original item.
  • Condition of the base: an uneven or cracked base has to be repaired first. Until the old tiles are removed, it is often impossible to say what condition the base is in.
  • Channel type and length: a longer channel, a channel in the middle of the room or a non-standard solution requires more precise setting and a more complex fall.
  • Underfloor heating: working around heating pipes is slower and needs more precision.
  • Access: an upper-floor flat with no lift means carrying screed and rubble by hand, which makes the job longer. Before you hand over renovation rubble or a skip load, check that the carrier is registered with the Environment Agency and ask for a waste transfer note.
  • Scope included in the quote: check whether the price includes tanking, the watertightness test and screed materials, or only setting, connecting and bedding the channel. The channel itself is often bought separately.

In a new build, installation is simpler. Screed depths are planned in advance, the waste is run exactly where needed and the fall is formed when the screed is laid. In a refurbishment, it often turns out that the old floor is too low or that the waste is in the wrong place. When comparing quotes, ask how the tradesperson deals with these situations and whether they are included or charged as extras.

How to prepare so the installation runs without delays

  • The channel is bought and on site: together with the installation instructions, feet, sealing collar and trap. If the plumber is waiting for a delivery, the screed cannot be laid.
  • The tiles are chosen: the plumber knows their thickness and sets the channel height without guesswork.
  • The old floor is broken out and the waste exposed: it can then be assessed straight away whether a standard connection will do. In homes built before 2000, have suspect materials tested before you drill or demolish; asbestos insulating board, lagging and sprayed coatings must be removed by an HSE-licensed contractor.
  • Water nearby: water is needed for mixing screed and for the tests, in the bathroom or close to it.
  • Coordination with other trades: other first-fix work in the bathroom, such as installing and recessing a concealed cistern frame or fitting a concealed shower valve (iBox), is best planned together with the channel, as part of the wider plumbing work.
  • Dates agreed with the tiler: the tiler should know when the screed is being laid and when it will be ready for tanking and tiling. If the tiler arrives before the screed has cured, the work is delayed or done badly.
  • The bathroom is out of use during curing: fresh screed must not be walked on or loaded. If it is the only bathroom in the home, it is wise to have an alternative for several weeks.
  • Stable conditions: a room without draughts or direct sunlight. In winter, keep the home heated, as cold slows curing.

Typical mistakes and how they show later

Incorrect floor fall. A fall of around 1.5 to 2 % towards the channel is usual. With less fall, water sits in the corners and puddles with limescale form. With an uneven fall, water runs out of the shower into the rest of the bathroom.

Too little fall on the waste pipe. Water drains slowly from the channel, backs up onto the floor during longer showers, and debris settles in the pipe.

Channel shifted out of position. If it is not properly supported, the screed lifts or tilts it during laying. The grate then does not sit flush with the tiles. Either it stands proud and becomes a trip hazard, or it sits low and water pools around it.

Thin screed over the pipe. The pipe should be covered by a sufficient depth of screed, usually around 4 cm. Otherwise cracks may form, transfer into the tiles and break the tanking.

Rigid joint to the waste. Screed moves slightly as it cures and with temperature changes. A rigid joint cannot cope with this movement and may crack. A leaking joint then lets water under the screed and lets drain smells into the room. Water spreads unnoticed and shows up as damp on a wall or in the property below.

Voids around the channel. When the screed does not fill the space under the channel, it flexes underfoot. The tiles around it crack and the grout joints open.

Missing tapes or one thin coat of tanking. Saving on tanking is the most expensive saving, because the repair means removing the tiles.

Tiling without a watertightness test. The fault is then only traced after the bathroom is finished and everything is covered.

Height set without knowing the tiles. Many channels have a height-adjustable grate frame, so a small difference can be taken up. But if much thicker or thinner tiles are chosen later, the adjustment range is not enough and the channel does not sit right.

How to check the finished work

At handover, it is worth going through these points before tiling and again at the end:

  • the top edge of the channel is at finished tile level and level along its length,
  • the channel does not move when pressed and there are no voids around it,
  • poured water drains smoothly and no puddles remain in the shower area,
  • the screed around the channel has no cracks,
  • the tanking is in two coats, with tapes at the corners and around the channel,
  • the flood test was carried out before tiling and the water level did not drop,
  • the trap is in place and there is no drain smell from the outlet,
  • the grate and trap can be removed for cleaning,
  • there are photos of the channel, the waste connection and the tanking taken before they were covered, or the plumber confirms that the joint was tested before bedding,
  • the installation instructions and technical data sheet for the channel are kept in case of a warranty claim.

Take your own photos before the screed is laid and before tiling. If a fault occurs later, you will know what is under the floor and exactly where the pipe runs.

Frequently asked questions

The guide price is €140.00 per piece. It applies to a standard case with the waste ready and enough floor depth. Chasing, rerouting pipework, repairing the base or raising the floor are usually charged as extras. The channel itself is often bought separately.