Laying concrete fencing blocks costs 4,00 € per piece of labour, according to the current price list. The foundation, reinforcement, concrete infill, posts, coping, gate and groundworks are priced separately according to the project and site conditions.
Types of work and their prices
Fencing blocks form a plinth, a solid wall or piers. The foundation, reinforcement and infilling of cavities must match the manufacturer's system and the structural design.
Posts carry the load from infill panels, the wicket gate and the main gate. For moving elements, the anchoring and foundation stiffness are what matter most.
Once reinforced and filled with concrete, these form a solid load-bearing section of the wall. The dimensions and reinforcement are set by the design, not just the fence height.
Fast installation of posts and precast panels. It needs accurate spacing, stable footings and safe handling of the panels.
A light and economical way to mark a boundary. The result depends on correct tensioning, end posts, struts and tensioning wires.
Stiffer than mesh and also suitable on top of a low wall. Post spacing and changes in ground level need to be respected.
Price the work from the price list
Enter quantities and the price recalculates instantly. You can adjust these rates in your price list.
All prices shown exclude VAT. Labour price covers labour only. Price incl. materials adds sundry materials (adhesive, primer, sealants, fixings). Tiles, flooring, paint and sanitaryware are chosen and bought by the client and are not included.
| Item | Unit | Price / unit | Quantity | Total |
|---|---|---|---|---|
| Fencing | ||||
| Laying concrete fence blocks | pcs | 4,00 € | - | |
| Building fence piers | lm | 22,05 € | - | |
| Install concrete fencing up to 1.8 m | lm | 20,05 € | - | |
| Install concrete fencing up to 2.1 m | lm | 23,05 € | - | |
| Install concrete fencing up to 2.4 m | lm | 24,06 € | - | |
| Fencing with DT 12/15 blocks | m² | - | ||
| Fencing with DT 20/25 blocks | m² | - | ||
| Remove old fencing | lm | 1,00 € | - | |
| Install fence post up to 2.4 m | pcs | 1,40 € | - | |
| Install fence post up to 2.7 m | pcs | 1,70 € | - | |
| Install fence post up to 3.8 m | pcs | 3,00 € | - | |
| Install fence strut up to 2.7 m | pcs | 1,70 € | - | |
| Install barbed wire extension arm | pcs | 1,40 € | - | |
| Tension straining wire | lm | 0,14 € | - | |
| Tension barbed wire | lm | 0,14 € | - | |
| Install fence frame | pcs | - | ||
| Install bespoke fence frame | pcs | - | ||
| Install fence panels | pcs | - | ||
| Install mesh fencing up to 1.4 m | lm | 1,70 € | - | |
| Install mesh fencing up to 1.8 m | lm | 1,90 € | - | |
| Install mesh fencing over 3.0 m | lm | 3,70 € | - | |
| Blockwork corner bonding | pcs | 1,00 € | - | |
| Foundations | ||||
| Concrete foundation for fence | m³ | 70,16 € | - | |
| Other works | ||||
| Other unspecified work in trade | hr | - | ||
How much it costs by scope
| Laying 300 Fencing Blocks Block-laying labour only, excluding the foundation and posts. | 1203,00 € |
| Blocks and Four Posts 300 blocks and a total of 8 m of built-up posts. | 1379,40 € |
| Foundation and Block Wall A model 4.8 m³ of foundation, 300 blocks, 8 m of posts and 4 bonded corners. | 1720,17 € |
Types of materials and their cost
Face blocks for a solid wall, plinth or piers. They must be rated for outdoor use and protected against water ingress from above.
Permanent formwork that is reinforced and filled with concrete. A hollow block alone is not yet a finished load-bearing structure.
The concrete class, bar diameter, cover and connection between the foundation and posts all follow from the loads and ground conditions.
A horizontal damp-proof layer separates the masonry from rising damp. Where it meets the ground, vertical protection is also needed.
The top edge must shed water away from the face of the wall. An overhang, fall and drip groove reduce staining and water damage.
Metal, timber or composite panels change the wind load on the structure. A solid infill transfers greater forces onto the piers than an open panel.
Preparation and build sequence for a fence
Before digging, the ownership boundary, gate position, utilities and the connection to the road are all checked. A fence should never be positioned purely on old posts or a kerb.
The site slope, rainwater run-off, made-up ground and the level difference between plots are all assessed. A fence should not end up unintentionally acting as a retaining wall.
The width, depth, reinforcement and layout of the foundation are chosen according to the ground, the fence height and weight. Dynamic and wind loads are factored in at the gate and solid sections.
Conduits for power, photocells, a bell, lighting and gate control are fitted before concreting. Later core drilling can compromise the reinforcement cover.
The highest point, the step heights and the position of coping elements are set out. On sloping ground, individual panels are stepped so they stay stable and visually level.
Method of work
- 01The fence line, corners, piers, wicket gate and vehicle gate position are marked out. Utilities and the plot boundary are checked before digging.
- 02The trench is dug down to firm, load-bearing ground. Soft spots, made-up ground or standing water are not simply covered with a thicker layer of concrete.
- 03The base, formwork and reinforcement are prepared. Vertical bars for piers are tied into the foundation, not loosely placed into the hole afterwards.
- 04The foundation is poured and its top surface levelled. Fresh concrete is protected from rapid drying out, rain and frost.
- 05Once sufficient strength is reached, horizontal waterproofing is applied. It must be continuous and carried through at corners and posts.
- 06The first course of blocks is set out dead level. Subsequent courses are laid in bond, with direction, height and plumb checked continuously.
- 07Cavities are reinforced and filled according to the system. Concrete is placed so that no voids remain and the blocks are not damaged by pressure.
- 08Long runs, changes in height and junctions between different structures are separated by a designed movement joint. The joint must run through the whole build-up.
- 09Anchors for infill panels, hinges and the gate drive are fixed into the load-bearing part of the posts. Expansion anchors are not placed close to the edge of a hollow block.
- 10The top edge is finished with a coping stone or cap with a fall and drip. The finished masonry is cleaned and inspected before handover.
- Rotary laser and levelling instrument
- Bricklayer's line, spirit level and plumb bob
- Vibrating equipment to suit the concreting method
- Bar bender and tying tools for reinforcement
- Block cutter with dust extraction
- Tape measure, square and spacing templates
5 common mistakes
Made-up ground or clay soil moves as moisture changes. The result is sagging sections, leaning posts and cracks that surface repairs cannot fix.
Water rises into the blocks, freezes in winter and leaves staining on the surface. Waterproofing cannot be properly added once the wall is built.
Concrete and masonry change volume with temperature and moisture. Without designed joints, the stress is released as a random crack.
The drive, hinges and wind create forces that an ordinary fence panel does not have to resist. A gate pier needs its own properly designed reinforcement, anchoring and foundation.
Water runs down the face, carries dirt into the joints and increases the risk of staining and frost damage. The top should have a fall and an overhang.
Too high a column of fresh concrete can shift or crack the blocks. The pour height and mix consistency are governed by the system's instructions.
Frequently asked questions
Laying concrete fencing blocks costs 4,00 € per piece of labour, according to the current price list. The foundation, reinforcement, concrete infill, posts, coping stones, infill panels and gate are priced separately.
There is no single universal figure. It depends on the soil, water, frost, the height and weight of the fence, and local conditions. The foundation is designed for load-bearing ground, and a structural engineer should review any higher-risk construction.
Yes, a continuous layer separating the masonry from rising damp is needed for a block fence. Where the wall meets the ground, vertical protection and safe water drainage are added as well.
Yes, but the steps, foundation and panels need to be designed in advance. A fence that retains soil may already function as a retaining wall and needs a matching structural and drainage design.
Mainly on long straight runs, where the height or thickness changes, and where different materials meet. The exact spacing comes from the construction system and design, not a universal rule of thumb.
Direction, plumb and height, even joint widths, cracks, coping elements, water drainage, panel anchors and gate operation are all checked. Photos of the reinforcement, ducts and waterproofing before they were covered are also important.
Related work
Price the whole project, not just one job
In the building work price list you pick items from every trade, and NUMIQ turns them into a client-ready quote.