Building work price list: Bonding / Earthing System
Enter quantities and the price recalculates instantly. You can adjust the rates in your price list.
All prices shown exclude VAT. Labour price covers labour only. Price incl. materials adds sundry materials (adhesive, primer, sealants, fixings). Tiles, flooring, paint and sanitaryware are chosen and bought by the client and are not included.
| Item | Unit | Price / unit | Quantity | Total |
|---|---|---|---|---|
Heating works cost | ||||
| Earth / bond heating system | pcs | €75.00 / pcs | pcs | enter quantity- |
| Remove & re-install radiator (complete) | pcs | €180.00 / pcs | pcs | enter quantity- |
| Remove gas / electric boiler | pcs | €110.00 / pcs | pcs | enter quantity- |
| Remove hot water cylinder | pcs | €109.00 / pcs | pcs | enter quantity- |
| Install & connect panel radiator | pcs | pcs | - | |
| Install bathroom towel radiator | pcs | €120.00 / pcs | pcs | enter quantity- |
| Lay underfloor heating insulation board | m² | €3.50 / m² | m² | enter quantity- |
| Underfloor heating pipe installation | m | €4.50 / m | m | enter quantity- |
| Install underfloor heating manifold | pcs | pcs | - | |
| Install gas condensing boiler | pcs | pcs | - | |
| Installation of air-to-water heat pump | pc | €950.00 / pc | pc | enter quantity- |
| Replace thermostatic radiator valve (TRV) | pcs | €19.00 / pcs | pcs | enter quantity- |
| Replace return valve | pcs | €19.00 / pcs | pcs | enter quantity- |
| Install circulation pump | pcs | pcs | - | |
| Pre-wire for smart thermostat connection | pcs | pcs | - | |
| Install & connect low-loss header | pcs | pcs | - | |
| Install expansion vessel | pcs | €54.00 / pcs | pcs | enter quantity- |
| Install recirculation pipework | pcs | pcs | - | |
| Install domestic hot water (DHW) / recirculation pump | pcs | pcs | - | |
| Thread pipework | pcs | €55.00 / pcs | pcs | enter quantity- |
| Flame weld metal pipework | pcs | €20.00 / pcs | pcs | enter quantity- |
| Pressure test heating system | hr | €130.00 / hr | hr | enter quantity- |
| Drain heating system | pcs | pcs | - | |
| Fill, bleed & balance heating system | hr | €70.00 / hr | hr | enter quantity- |
| Pipework for radiators | lm | €9.00 / lm | lm | enter quantity- |
| Flush & clean existing heating system | hr | €50.00 / hr | hr | enter quantity- |
| Pipe freezing | pcs | €50.00 / pcs | pcs | enter quantity- |
| Cap off radiator | pcs | €65.00 / pcs | pcs | enter quantity- |
| Fill heating system | pcs | pcs | - | |
| Chase heating pipes in floor | lm | €24.00 / lm | lm | enter quantity- |
| Concrete-in heating pipes in floor | lm | €6.50 / lm | lm | enter quantity- |
| Install radiator bracket | pcs | €17.00 / pcs | pcs | enter quantity- |
| Install thermostatic radiator valve (TRV) & head | pcs | €19.00 / pcs | pcs | enter quantity- |
| Pressurise & bleed radiator | pcs | €12.00 / pcs | pcs | enter quantity- |
What bonding and earthing of the heating system mean and when they are done
In everyday use, bonding and earthing are treated as the same thing. Technically they mean different things. Earthing connects the electrical installation to earth, either through the earth provided with the electricity supply or through an earth electrode, such as an earth rod driven into the ground. Protective bonding means that the metal parts in the building are connected to each other and to this earth. When people talk about earthing the heating, they almost always mean bonding.
If the insulation in a washing machine or water heater is damaged and a live conductor touches the metal casing, the protective conductor carries the fault current away and the circuit breaker or RCD switches the circuit off. Bonding adds equalisation of potential. Metal parts that a person can touch at the same time are kept at the same voltage. No dangerous voltage difference can then arise between a radiator and a tap that could pass through a person, even if a voltage enters the house along metal pipework from outside.
There are two levels:
- Main protective bonding connects the incoming water and gas services, the heating and metal structural parts to the main earthing terminal. This is usually near the consumer unit or close to where the services enter the house, but its position varies from house to house.
- Supplementary bonding is carried out in locations with increased risk, such as a bathroom or a boiler room. It connects metal parts that are close to each other. In a bathroom it can be omitted when certain conditions are met, for example when all circuits are protected by an RCD and the main bonding is in good order. An electrician or the electrical design decides whether it is needed.
Bonding of the heating is dealt with in these situations:
- in a new build,
- when the boiler is replaced,
- when metal pipework is replaced with plastic,
- whenever an electrical inspection finds that the bonding is missing or broken.
What to check before ordering the work
This is work on electrical protection, not a routine plumbing job. Before calling a tradesperson, clarify these points:
- Who does the work: the clamps and conductors are fitted by a qualified electrician. A heating engineer can prepare the pipework and help with the clamps.
- Who issues the certificate: the electrician who carries out and tests the work should issue the appropriate electrical certificate. Ask in advance whether this is included and whether the electrician is registered with a recognised scheme.
- Is there a main earthing terminal and a working earth: if not, the bonding has nowhere to connect and the earthing arrangement has to be sorted out first. This is a separate electrical job, which may include an earth electrode and measurement of its resistance.
- What is to be connected: only the boiler and pipework in the boiler room, or also the cylinder, manifold and metal parts in the bathroom. The scope is set by the electrical design, or in older houses by the electrician during the survey.
- Change to plastic pipework: plastic does not conduct electricity. If part of the steel or copper pipework is replaced with plastic, the original bonding path is broken and the metal sections on either side are left unconnected. The bonding has to be added, ideally as part of the plan for the alterations, not only at the next inspection.
- Where connections will stay accessible: clamps must not be plastered over or hidden behind tiles. If pipes run behind tiling or in a duct, agree on access panels in advance.
- Flats: risers are part of the common parts of the building, so the procedure must be agreed with the managing agent or freeholder.
- Larger refurbishment: if the bonding is part of wider building work, check with local building control what the overall work requires. A new circuit, a consumer unit replacement or work in a bathroom is notifiable under Part P in England and Wales, so use an electrician registered with a competent person scheme (e.g. NICEIC or NAPIT) or notify building control before you start.
How the work proceeds step by step
- Survey: the electrician checks whether there is a main earthing terminal, where the existing bonding runs and which parts of the heating are metal.
- Design: the electrician decides which parts need connecting and the routes for the conductors. In a new build this is covered by the electrical design.
- Preparing the pipework: paint and rust are removed from the pipe at the clamp position, down to bare metal.
- Fitting clamps: earth clamps are fitted to the cleaned pipe and must sit firmly on bare metal.
- Running conductors: a green-and-yellow conductor is run from the clamps to the bonding terminal. It is fixed in place and protected where it could be damaged.
- Connecting the boiler and equipment: the frame of the boiler, hot water cylinder or manifold is connected according to the manufacturer's instructions.
- Testing: the continuity of the protective conductors and bonding is measured.
- Certification and handover: the electrician records the test results on the certificate. The customer receives it together with information on what has been connected.
What is connected and which materials are used
The following heating components are usually bonded:
- metal central heating pipework where it enters the boiler room or at the manifold,
- the frame of the boiler, heat pump or electric water heater,
- a metal hot water cylinder and its connections,
- metal parts in the bathroom, if required by the design or the electrician.
Connections are made with earth clamps or straps made of a material that does not corrode with the pipe in question. Copper needs a different clamp from galvanised steel.
The conductor has green-and-yellow insulation and a cross-section in line with BS 7671:2018+A4:2026, the current IET Wiring Regulations. As a guide:
- main protective bonding: the conductor should be at least half the size of the earthing conductor, and not less than 6 mm² for copper. Some supply types require a larger size,
- supplementary bonding: at least 2.5 mm² if the conductor is mechanically protected, for example in trunking or conduit, and at least 4 mm² if it runs unprotected.
The exact size for a specific house is set by the electrician based on the supply type, the protective conductors in the consumer unit and the route of the conductor.
Special rules apply to gas pipework. The bonding is made on the consumer's side of the gas meter, inside the house. Never interfere with the gas installation yourself - gas work must be done by a Gas Safe registered engineer. If you smell gas during the work, do not switch lights or electrical appliances on or off, do not use any naked flame, turn off the gas at the emergency control valve, open the windows and leave the area. Only once outside, call the free 24-hour National Gas Emergency Service on 0800 111 999 (0800 002 001 in Northern Ireland). For LPG, call the number shown on the tank or meter.
What the price of bonding and earthing the heating depends on
The guide price for the work is €75.00 per item. When comparing quotes, ask what one item means. It may be one connected point, meaning a clamp with a conductor, or the bonding of the whole system in the boiler room.
Bonding is cheapest in a new build or when the whole heating system is replaced, as described in the overview of heating work. The pipes are exposed, the terminal is close to the boiler room and a few short conductors are enough. The price rises in these situations:
- old pipework: removing paint and rust adds time at every point,
- pipes in walls or floors: opening up and making good can cost more than the connection itself,
- long route to the terminal: more cable and more work fixing it,
- more parts to connect: boiler, cylinder, manifold or metal sections left after a change to plastic, each part means another connection,
- no earth electrode: excavation, a new electrode and testing can multiply the total cost,
- flats: work on risers needs agreement and sometimes coordination with other flats,
- certification: the electrical certificate may be included in the quote or charged separately.
What makes the work easier and what slows it down
- clear access: the boiler room, the area around the boiler, cylinder and manifold, and the consumer unit should be cleared,
- documentation: the electrical design, previous certificates or inspection reports and the boiler manual show what is already connected and what the manufacturer requires,
- timing: bonding is done while the pipes are exposed, before tiling, plasterboard and closing ducts, and before any radiator boxing in,
- sequence of trades: when the electrician follows straight after the heating engineer, for example after draining the heating system and replacing pipework, there is no downtime and nobody has to open up finished work,
- consent in flats: it is better to have agreement from the managing agent before the electrician arrives.
Typical mistakes and how they show up later
Clamp fitted over paint or rust
There is no conductive contact. The connection looks fine, but it fails the continuity test and gives no protection in a fault.
Bonding connected to the neutral instead of the protective conductor
This is a serious fault. In a fault it can put a voltage onto the very metal parts that are meant to be safe. An inspection will reveal it.
Nobody restores the broken bonding after a change to plastic
Metal sections are left unconnected. The problem usually only shows up at an inspection or when an appliance develops a fault.
Unsuitable combination of metals at the connection
The connection gradually corrodes, its resistance rises and eventually it stops conducting.
Conductor run loosely across the room
It is damaged by handling or moisture and the bonding is quietly broken.
Connections hidden behind tiles
They cannot be checked during an inspection and tiles must be broken out for a repair.
The heating engineer "connects the frame" alone, without an electrician and without testing
Nobody knows whether the protection works, and there is no certificate.
Heating or water pipes must never be used as a substitute for the earthing of the electrical installation. The heating is connected to the protection, but does not provide it.
How to check the finished work
Only testing confirms that the bonding works, it cannot be judged by eye. On handover you can still check several things:
- the clamps are firmly tightened and sit on clean metal,
- the conductors have green-and-yellow insulation and are fixed along their entire route,
- the boiler, cylinder and agreed metal pipework are connected,
- the connections remain accessible and are not plastered over,
- clamps carry the safety label and conductors at the bonding terminal are labelled or recorded,
- a continuity test has been carried out,
- you have received an electrical certificate with the electrician's name and details.
Frequently asked questions
Roughly €75.00 per item. The final amount depends on the factors described in the price section. When getting a quote, check whether an item means one connection or the whole system and whether the certificate is included.
A heating engineer can prepare the pipework and help fit the clamps. Connecting to the protective system and testing is the job of a qualified electrician, who also issues the electrical certificate.
Not always. A metal radiator connected only to plastic pipes may have no path to earth that could bring an external potential into the room. Whether a connection is needed is decided by the electrician based on the applicable standards, the type of room and what is nearby. This is worth checking during radiator removal and installation.
It is always checked when a boiler is replaced. The boiler frame must be connected as the manufacturer's instructions require, and the boiler's electrical connection is part of the testing. Whether the pipework also needs bonding depends on its material. Metal pipes are bonded, with plastic pipework the electrician decides.
There are usually no clamps with a green-and-yellow conductor on the pipes near the boiler or water meter. Only a check by an electrician gives certainty - the electrician tests continuity and confirms that the house has a working earth.
It is checked during periodic inspections of the electrical installation and always after work on the heating, plumbing or consumer unit. Electrical Safety First recommends an Electrical Installation Condition Report (EICR) at least every 10 years for an owner-occupied home, and landlords must have one done at least every 5 years. If the RCD trips for no obvious reason or you feel a slight tingle when touching metal parts, stop touching them, warn others in the household, switch off the main switch if it is safe to do so and call an electrician immediately.
Related work
When and how to drain a central heating system, what to watch for with radiators and underfloor heating, and how to refill and bleed it.
How a radiator is taken off the wall and refitted, what makes the job harder, what to consider in a flat and how to check the finished work.
How a radiator is boxed in with plasterboard, timber, MDF or metal, what to watch with airflow and valves, and how to check the finished cover.
How underfloor heating pipes are covered with screed, which screed to choose, why the pressure test matters and how to heat the floor up for the first time.
How a floor chase for heating pipes is cut, what makes the job harder, what to watch for in a block of flats and how to check the finished work.
How radiator valves are fitted and replaced, which valve types to choose, common mistakes to avoid and how to check the finished work.
Blog
Price the whole project, not just one job
Choose items from all trades and NUMIQ turns them into a quote for your own project or your customer's project.